As construction continues on the future SB Express Lanes, 55-hour directional I-10 freeway closures and I-10/I-15 connector closures will occur over the next several months. These closures, throughout the project corridor between the Los Angeles/San Bernardino County Line and I-15, are necessary for crews to remove and repave portions of the freeway.

This past weekend there was a 55-hour directional freeway closure on eastbound I-10 between Monte Vista Avenue and Central Avenue. Beginning in late April, the I-10/I-15 connectors will be closed for 55-hours for four weekends in a row. The tentative schedule is:

Westbound I-10 to the northbound and southbound I-15 connector closed:

  • Friday, April 23 at 10:00 p.m. through Monday, April 26 at 5:00 a.m.
  • Friday, April 30 at 10:00 p.m. through Monday, May 3 at 5:00 a.m.

Detour: Westbound I-10, exit on to Milliken Avenue, turn right on Milliken Avenue to access eastbound I-10 to northbound/southbound I-15.

Northbound I-15 to the westbound I-10 connector closed:

  • Friday, May 7 at 10:00 p.m. through Monday, May 10 at 5:00 a.m.
  • Friday, May 14 at 10:00 p.m. through Monday, May 17 at 5:00 a.m.

Detour: Northbound I-15 to eastbound I-10, exit on to Etiwanda Avenue, turn left on to Etiwanda Avenue to access westbound I-10.

Construction is dynamic and schedules may change. Please plan ahead, leave early, and allow extra time to reach your destination. For real-time closures and detours, bookmark the project’s live, interactive Google Map at https://bit.ly/i10ExpressLanesGoogleMap. Sign up to receive construction alerts via email for weekly information about project construction, closures, and detours at goSBCTA.com/i10corridor.