The San Bernardino County Transportation Authority (SBCTA) and the City of Redlands, in coordination with Caltrans District 8, will widen the I-10 westbound on-ramp and I-10 eastbound off-ramp at University Street, as well as restripe University Street from Citrus Avenue to Central Avenue. The project will:
- Reduce congestion, improve safety, and improve traffic operations along University Street between Citrus Avenue and Central Avenue.
- Install new traffic signals at the eastbound I-10/University Street intersection and the westbound I-10/University Street/Central Avenue intersection.
- Provide street improvements within the project limits including drainage improvements, pavement construction, and landscaping.
- Provide Americans with Disabilities Act (ADA) compliant curb ramps, pedestrian push buttons and signals, and detectable warning surfaces at intersections where crosswalks are included.
Fact Sheets